Key takeaways
- The Commissioner of Metro Rail Safety (CMRS) cleared the elevated Pink Line stretch on 28 October 2026 from Kalena Agrahara to Tavarekere, about 7.5 km and 6 stations.
- The inauguration is set for 13 November 2026, with Prime Minister Narendra Modi expected. Public service is reported to start on 15 November.
- The full Pink Line runs about 21 km from Kalena Agrahara to Nagawara with 18 stations: 6 elevated and 12 underground.
- The underground stretch from Dairy Circle to Nagawara is still in fit-out and trials. One report puts its target at May 2027.
- Jayadeva Hospital (Yellow Line) and MG Road (Purple Line) are interchanges from day one. Nagawara links to the Blue Line once that line opens.
- A metro station nearby does not make land buildable. Check distance, zoning and risk for the exact survey number first.
Where is the Pink Line today?
Tap any station to see its section, interchange and the areas around it.
Pick a station
Each station card shows its section status and a link to see the land around it on the live map.- → Pink Line latest status and opening date (November 2026)
- → Route map and all 18 stations
- → Opening timeline: what happened and what is next
- → The three interchanges
- → What the Pink Line means for land near stations
- → How to check land near a station on TalkingLands Insights
- → Frequently asked questions
The Pink Line metro in Bangalore, Namma Metro Line 5, is the north–south line that runs from Kalena Agrahara on Bannerghatta Road to Nagawara on the Outer Ring Road, tunnelling under MG Road and Shivajinagar on the way. After years of shifting targets, the first part of it is finally close to carrying passengers.
Pink Line metro Bangalore: opening date and latest status (November 2026)
On 28 October 2026 the elevated Pink Line stretch between Kalena Agrahara and Tavarekere received safety clearance from the Commissioner of Metro Rail Safety (CMRS). The inspection covered track alignment, signalling, traction power, emergency arrangements and the results of trial runs.
The opening date is now set. Bengaluru South MP Tejasvi Surya posted on 2 November that the inauguration will be on 13 November 2026, and Prime Minister Narendra Modi is expected to open the 7.5 km stretch. A Metro official quoted by Prajavani, as reported by Urban Acres, said public service would begin on 15 November, two days after the inauguration. An earlier report had said service would start the day after the inauguration, so check BMRCL’s notice for the first passenger train.
What we know about launch service so far:
- Trains: six trains to start with, built by BEML (one report says five to six).
- Frequency: every 6 minutes at peak hours and every 10 minutes at other times.
- Network: with this stretch, Namma Metro crosses about 100 km of operational lines.
- Fares: not published yet.
If you want station-by-station progress notes, our Pink Line 18-station status tracker and the southern stretch opening update go deeper on each station.
Pink Line route map and all 18 stations
The Pink Line is about 21 km long. The southern third is elevated along Bannerghatta Road. From Dairy Circle the line drops underground and stays there through the city centre until Nagawara. Use the station picker above for the areas each station serves.
| # | Station | Type | Status (6 Nov 2026) | Interchange / note |
|---|---|---|---|---|
| 1 | Kalena Agrahara | Elevated | CMRS cleared; inauguration 13 Nov | Southern terminus on Bannerghatta Road |
| 2 | Hulimavu | Elevated | CMRS cleared; inauguration 13 Nov | – |
| 3 | IIMB | Elevated | CMRS cleared; inauguration 13 Nov | – |
| 4 | JP Nagar 4th Phase | Elevated | CMRS cleared; inauguration 13 Nov | Planned Orange Line interchange |
| 5 | Jayadeva Hospital | Elevated | CMRS cleared; inauguration 13 Nov | Interchange with the Yellow Line (operational) |
| 6 | Tavarekere | Elevated | CMRS cleared; inauguration 13 Nov | Last elevated station |
| 7 | Dairy Circle | Underground | Trials and fit-out; 2027 target | Underground section starts; proposed Red Line link |
| 8 | Lakkasandra | Underground | Trials and fit-out; 2027 target | – |
| 9 | Langford Town | Underground | Trials and fit-out; 2027 target | – |
| 10 | National Military School | Underground | Trials and fit-out; 2027 target | – |
| 11 | MG Road | Underground | Trials and fit-out; 2027 target | Interchange with the Purple Line (operational) |
| 12 | Shivajinagar | Underground | Trials and fit-out; 2027 target | – |
| 13 | Cantonment | Underground | Trials and fit-out; 2027 target | Link to Bengaluru Cantonment railway station |
| 14 | Pottery Town | Underground | Trials and fit-out; 2027 target | – |
| 15 | Tannery Road | Underground | Trials and fit-out; 2027 target | – |
| 16 | Venkateshpura | Underground | Trials and fit-out; 2027 target | – |
| 17 | Kadugundanahalli | Underground | Trials and fit-out; 2027 target | – |
| 18 | Nagawara | Underground | Trials and fit-out; 2027 target | Northern terminus; interchange with the Blue Line (under construction) |
Station names in BMRCL documents sometimes differ slightly (for example “Mahatma Gandhi Road” for MG Road and “Cantonment Railway Station” for Cantonment). The order above runs south to north.
Pink Line opening timeline: what happened and what is next
The Pink Line has missed several announced dates, so it helps to see the sequence in one place.
- 2020–2021: Tunnel boring starts on the underground packages, built by L&T, Afcons and ITD-Cem.
- January 2026: Trials begin on the elevated stretch with a six-coach BEML train.
- September 2026: BMRCL receives the fitness certificate after an independent inspection and moves towards Railway Board and CMRS approvals.
- 28 October 2026: CMRS clears the elevated stretch, Kalena Agrahara to Tavarekere.
- 13 November 2026: Inauguration of the elevated stretch, with the Prime Minister expected. Public service reported from 15 November.
- Late 2026 onwards: Trial runs on the underground stretch, starting between Dairy Circle and Shivajinagar.
- 2027 (target): Underground stretch to Nagawara. One report links it to a May 2027 target that depends on signalling tests, platform screen doors and inspections.
Where the reports differ: earlier targets for the elevated stretch ranged from March 2026 to August and then mid-October 2026. Dates for the underground section have also moved. Plan around the stretch that has actually been cleared, not around a launch-day promise.
The CMRS-cleared elevated stretch on the TalkingLands metro layer. Tap the map to open it live.
The three interchanges that change commutes
A single line helps the people who live next to it. Interchanges are what make it useful to the rest of the city.
- Jayadeva Hospital (Yellow Line): Pink Line riders can change for Electronic City and Bommasandra. This interchange works from the day the elevated stretch opens.
- MG Road (Purple Line): connects the south to the east–west line towards Whitefield and Challaghatta once the underground stretch opens.
- Nagawara (Blue Line): the Blue Line is the airport line on the Outer Ring Road. Nagawara becomes a junction once both lines run. Our Blue Line status update tracks its trials.
JP Nagar 4th Phase is also planned as an interchange with the future Orange Line, and Cantonment station is designed to link with Bengaluru Cantonment railway station.
What the Pink Line means for land near its stations
Most people searching for the Pink Line want one of two things: when they can ride it, or whether a home or plot near a station is a good buy. On the second question, a few honest points.
The elevated south opens first. Hulimavu, Arekere, Gottigere, Bilekahalli and JP Nagar get a working station years before the city-centre stations. That is the part of the corridor where the change is real this year.
The underground core is about access, not new land. Langford Town, Shivajinagar, Cantonment and Pottery Town are already dense. The metro improves access, but there is little open land, so most decisions here are about apartments and commercial space.
The north end sits on the Outer Ring Road. Tannery Road, Venkateshpura, Kadugundanahalli and Nagawara gain a direct line to the city centre, and Nagawara gains the Blue Line junction later.
We do not quote price changes here. Listing prices near stations often include a “metro premium” before the line even opens. Three checks protect you from paying for the wrong plot:
How to check land near a Pink Line station on TalkingLands Insights
TalkingLands Insights puts the Pink Line, its stations and survey parcels on one map, so you can check a specific plot in a couple of minutes.
- Search the locality, address or survey number in the search bar.
- Open Connectivity → Metro. The Pink Line and its stations appear on the map with the other Namma Metro lines.
- Tap the survey parcel you are looking at to see its details, and judge the real route to the nearest station on the satellite view.
- Turn on Boundary → Master Plan to see the land-use zone, and Risk layers such as Lake Buffer, Rajakaluve and Flood Index.
- Click Get Report for a property report on that parcel, then confirm with the authority and a lawyer before you pay an advance.
What the map shows: the metro line and stations, survey boundaries, master plan zoning and risk layers. What it does not show: future fares, the exact location of station exits, or a guarantee on price growth.
Survey parcels around Hulimavu and Kalena Agrahara stations. Tap the map to check your own land.
Is your land near a Pink Line station?
See the metro line, the nearest station, the zoning and the risk layers for any survey number. Sign up free and get 5,000 coins.
Check your land freeFrequently asked questions
The elevated stretch from Kalena Agrahara to Tavarekere received CMRS safety clearance on 28 October 2026. Its inauguration is set for 13 November 2026, with Prime Minister Narendra Modi expected to open it. Public service is reported to start on 15 November, though one earlier report said the day after the inauguration. The underground stretch from Dairy Circle to Nagawara is targeted for 2027.
The Pink Line has 18 stations over about 21 km: 6 elevated stations from Kalena Agrahara to Tavarekere and 12 underground stations from Dairy Circle to Nagawara.
The elevated southern stretch along Bannerghatta Road opens first: Kalena Agrahara, Hulimavu, IIMB, JP Nagar 4th Phase, Jayadeva Hospital and Tavarekere, about 7.5 km.
At Jayadeva Hospital for the Yellow Line and at MG Road for the Purple Line. Nagawara will connect to the Blue Line once that line opens. A link to Cantonment railway station is also planned.
Reports say six trains will run at launch, every 6 minutes at peak hours and every 10 minutes at other times. BMRCL has not published fares for the line yet.
Open TalkingLands Insights, search the locality or survey number, turn on Connectivity and then Metro. The Pink Line and its stations appear on the map with survey parcels, so you can see the distance and then check zoning and risk layers for the same parcel.
This article is general information as of 6 November 2026 and not legal advice or investment advice. Metro timelines change. Check the latest BMRCL announcements, and verify any property with the authority and a qualified lawyer before you buy.